In advance of their November 18th Public Hearing at the Saugerties Planning Board, engineers for SOLOHS submitted a revised short form EAF.
There is only one significant change and this has to do with the re-routed road. The road down to Route 212 will now have to cross wetlands and so the question about encroaching on wetlands is now answered in the affirmative.
We note the continued omission of a description of details in answer to question 20:
20.Has the site of the proposed action or an adjoining property been the subject of remediation (ongoing or completed) for hazardous waste?
This question is answered in the affirmative, but neither the original, nor the revised, EAF supply the required details.
Here is a copy of the revised EAF:
2025-10-22-SOLOHS-EAF-Revised
A reminder that many, if not most, documents from the Public File associated with the project can be found in a shared Google Drive at:
https://drive.google.com/drive/folders/1W41ykw_tlGHlCXSpNOwzdlS6h27dfnPO?usp=sharing
A FOIA request was made for any response from the Board’s Planning Consultant, but none was forthcoming as of Thursday November 13 at noon.